Nikolovorobinsky 9

12.03.2021

The RBM Company took part in the reconstruction of the cultural heritage object according to the author’s projector by the architect Sergey Skuratov on Serebryanicheskaya embankment.

The work was carried out in cramped conditions in the center of Moscow. The main task is to preserve the historical facade of the building.

Demolitioning was carried out with the help of small mechanization, working from the floors. Also, mechanized demolitioning was used with a heavy equator-destroyer with a grip with an arrow length of 28 meters.

The task of the RBM company also included works on clearing and planning the site for new construction.

The demolitioning project was completed successfully and on time.